Deployment at Bishopgate Gardens Bishopgate Gardens, Preston

Event Started
2022-05-04 12:00
Report Published
2022-04-12 20:44
Last Updated
2022-06-05 20:42
Event Finished
2022-05-27 17:00

Our engineers will be finishing the final phase of network build at Bishopgate Gardens to connect residents to National Fibre's Internet access service.

Timeline (most recent first)
  • 2022-05-26
    00:00:00

    Installation complete!

  • 2022-05-25
    09:34:00

    Service has been handed over.

  • 2022-05-19
    15:14:00

    We are expecting handover to be on 7th June.

  • 2022-05-17
    14:30:00

    Fibre installation is complete. We now await provisioning and handover.

  • 2022-05-17
    10:00:00

    Fibre installation is taking place this morning. Once complete, we await the provisioning of service to the buildings.

  • 2022-05-12
    11:27:00

    Fibre work in Building B is complete.

  • 2022-05-06
    10:30:00

    Fibre work in Building A has completed. There is further work required in Building B.

  • 2022-05-04
    17:30:00

    Further cabling and fibre splicing work is required to complete the works.

  • 2022-05-04
    14:00:00

    Network switching and optical equipment is being installed.

  • 2022-05-04
    11:30:00

    Fibre surveys are underway.

  • 2022-05-02
    09:30:00

    Network switching equipment has been despatched.

  • 2022-04-25
    12:04:00

    Optical network equipment has been delivered to site.

  • 2022-04-15
    05:41:00

    Optical network equipment is enroute.

  • 2022-04-14
    11:30:00

    Access points have been delivered to site.