Our engineers will be finishing the final phase of network build at Bishopgate Gardens to connect residents to National Fibre's Internet access service.
Deployment at Bishopgate Gardens Bishopgate Gardens, Preston
- Event Started
- 2022-05-04 12:00
- Report Published
- 2022-04-12 20:44
- Last Updated
- 2022-06-05 20:42
- Event Finished
- 2022-05-27 17:00
Timeline (most recent first)
-
2022-05-26
00:00:00Installation complete!
-
2022-05-25
09:34:00Service has been handed over.
-
2022-05-19
15:14:00We are expecting handover to be on 7th June.
-
2022-05-17
14:30:00Fibre installation is complete. We now await provisioning and handover.
-
2022-05-17
10:00:00Fibre installation is taking place this morning. Once complete, we await the provisioning of service to the buildings.
-
2022-05-12
11:27:00Fibre work in Building B is complete.
-
2022-05-06
10:30:00Fibre work in Building A has completed. There is further work required in Building B.
-
2022-05-04
17:30:00Further cabling and fibre splicing work is required to complete the works.
-
2022-05-04
14:00:00Network switching and optical equipment is being installed.
-
2022-05-04
11:30:00Fibre surveys are underway.
-
2022-05-02
09:30:00Network switching equipment has been despatched.
-
2022-04-25
12:04:00Optical network equipment has been delivered to site.
-
2022-04-15
05:41:00Optical network equipment is enroute.
-
2022-04-14
11:30:00Access points have been delivered to site.